You may have noticed that there is an increase in activity around the site of our new building. This is exciting news!
With this increased activity and the need to relocate utility poles comes the need to change the way that our walkers get to and from school.
We are providing a drawing of where the new walker path will be as indicated by the red line on the map. This change will happen very quickly so that they will be rerouted on April 24th. Please review the timeline below and any anecdotal information.
4/17 & 4/18 – Tree and shrub removal
4/18/2024 – Security fencing installation. Openings will be left at the location of the current crosswalk and at the concrete walk intersection at the school entrance. These will be gated and locked once the other pathway is established. Students will still use the traditional path until 4/24
4/20/2024 – New temporary sidewalk is being installed.
4/22-4/23 – New temporary crosswalk will be painted.
4/24/2024 – New pathway will be opened and existing will be closed.
Please call the school office if you have any questions or concerns.